Skip to content
Loading map…

Aspen Heights Retirement Residence - Swimming Pool

15 Aspen Summit Drive SW Calgary AB T3H 6G2 · Aquatic Facility

9 inspections

  1. Demand Inspection

    0 infractions

  2. Monitoring Inspection

    0 infractions

  3. Risk Management Inspection

    0 infractions

  4. Risk Management Inspection

    1 infraction

    • 02. Is the bacteriological quality of the water in this pool satisfactory (Critical)?
      • TC present. Treat and resample.
  5. Risk Management Inspection

    0 infractions

  6. Demand Inspection

    2 infractions

    • 02. Is the bacteriological quality of the water in this pool satisfactory (Critical)?
      • The water sample taken on December 7, 2023 had total coliforms present.-Resample.
    • 03. Is the bacteriological quality of the water in this pool satisfactory (Non-Critical)?
      • The water sample taken on December 7, 2023 had a HPC count of 150cfu/ml.-Resample
  7. Initial Inspection

    0 infractions

  8. Risk Management Inspection

    5 infractions

    • 04. Is the chemical quality of the water in this pool satisfactory (Critical)?
      • 1. Free chlorine was measured at 0.13ppm- Free chlorine must be maintained at 1ppm or greater.
    • 05. Is the chemical quality of the water in this pool satisfactory (Non-Critical)?
      • 1. Total alkalinity was measured at 21ppm.- Maintain TA between 60-180ppm.
    • 07. Are the filtration, circulation and disinfection systems used to maintain water quality working properly (Non-Critical)?
      • 1. Water level was below skimmers, no surface water was being recirculated.- Ensure water level is adequate to allow for maximized surface level filtration through the skimming devices.
    • 16. Are proper testing, monitoring, and other records being properly maintained?
      • 1. Automated controller set points are not recorded.- Record automated controller set points for ORP and pH.
    • 17. Does the pool have adequate written policies, plans and posted rules and safety information to ensure that the pool is operating in a safe manner?
      • 1. Anti-entrapment plan is incomplete, missing sump dimensions and the model# of the pump is inconsistent with the model #'s on the pump curve diagram.- Sump is field fabricated, please submit drawings showing sump dimensions.- Confirm recirculation pump model number and include the correct pump curve diagram for max flow rate determination.2. Water quality incident response plan is incomplete.- Please complete, comments provided by email. Ensure updated copy is kept onsite.
  9. Demand Inspection

    6 infractions

    • 03. Is the bacteriological quality of the water in this pool satisfactory (Non-Critical)?
      • The water sample on August 16, 2023 had a HPC count of 110 cfu/ml.-Submit a resample.
    • 04. Is the chemical quality of the water in this pool satisfactory (Critical)?
      • 1. Free chlorine was measured at 0.13ppm- Free chlorine must be maintained at 1ppm or greater.
    • 05. Is the chemical quality of the water in this pool satisfactory (Non-Critical)?
      • 1. Total alkalinity was measured at 21ppm.- Maintain TA between 60-180ppm.
    • 07. Are the filtration, circulation and disinfection systems used to maintain water quality working properly (Non-Critical)?
      • 1. Water level was below skimmers, no surface water was being recirculated.- Ensure water level is adequate to allow for maximized surface level filtration through the skimming devices.
    • 16. Are proper testing, monitoring, and other records being properly maintained?
      • 1. Automated controller set points are not recorded.- Record automated controller set points for ORP and pH.
    • 17. Does the pool have adequate written policies, plans and posted rules and safety information to ensure that the pool is operating in a safe manner?
      • 1. Anti-entrapment plan is incomplete, missing sump dimensions and the model# of the pump is inconsistent with the model #'s on the pump curve diagram.- Sump is field fabricated, please submit drawings showing sump dimensions.- Confirm recirculation pump model number and include the correct pump curve diagram for max flow rate determination.2. Water quality incident response plan is incomplete.- Please complete, comments provided by email. Ensure updated copy is kept onsite.